Extracting sand and gravel, mineral water or other minerals without a license is not allowed. The subsoil belongs to the state, and owning a plot of land does not give you the right to use the subsoil. The exception is extracting locally significant minerals for household use on a plot in private possession. Applications are reviewed by the National Agency of Mineral Resources (in some cases, the license is issued by the relevant ministry of the Autonomous Republic of Adjara). A license may be obtained by an individual or a legal entity, including a foreigner, if registered as a taxpayer.

Stages of obtaining a license

  1. Application. You fill in the application electronically, on rs.ge. In it you must indicate the type of resource, the quantity, the location with approximate X and Y coordinates, and the term of the license. You will need a registry extract (for a company) or an ID card. If the plot is privately owned, you must also attach the owner’s notarized consent.
  2. Review of the application: 5 working days. Within this period the Agency checks the documents. If there is a defect, it will notify you and give you no more than 5 working days to correct it. If you do not correct the defect within this period, the application will be left unreviewed.
  3. Geoinformation package: 30, 15 or 10 working days. After you pay the fee, the Agency prepares the package, which includes a sketch of the territory, a topographic map and an engineering-geological opinion. The faster you need it, the more expensive it is. According to the Agency’s website, for a 30 working day period the package costs 400 lari for an area of up to 10 hectares and 500 lari for an area of more than 10 hectares. For 15 days, these amounts are 1 400 and 1 600 lari respectively, and for 10 days, 2 500 and 3 500 lari. For underground waters and carbon dioxide, the size of the territory is not taken into account: 200 lari for 30 days, 500 lari for 15 days, 1 000 lari for 10 days. The amounts include VAT.
  4. Position of other agencies: 5 working days. The Agency sends the package to the agencies and organizations concerned with the matter. Each has 5 working days to respond, with a possible extension of up to another 5, however, if the entity involved in the proceedings must notify the license issuer of the above by an interim notice, with appropriate justification, within no later than 3 days of receiving the notice. If no comments or refusal are submitted within the deadline, the matter is considered agreed. The entire process before the announcement of the auction or the refusal to announce it must not exceed 4 months.
  5. Auction. A license is, as a rule, issued at an electronic auction. To participate, you must register in advance and pay a guarantee amount (10% or 50% of the starting amount) and a fee of 200 lari.
  6. After winning. You must pay the remaining amount within 15 calendar days. If you miss this deadline, you have another 15 working days, but for each day of delay you will pay a penalty of 1% of the amount due. If you do not pay even then, the auction is considered failed.
  7. Issuance of the license. You will receive the license on the 10th working day after confirmation of payment of the final amount. In urgent cases, you can speed up the issuance of the license for an additional fee.

In some cases, a license is issued without an auction. For example, when up to 5 000 cubic meters of fresh water per year is extracted from a well or spring in private ownership.

What the license costs

When obtaining a license, you pay once a license fee of 200 lari, the fee for the geoinformation package and the amount fixed at the auction. To this is added the fee for the use of natural resources, the amount of which depends on the type and volume of the resource.

How long a license is issued for

The term depends on the type of mineral. A license for energy minerals is issued for up to 45 years, for ores of ferrous and non-ferrous metals up to 40 years, for construction materials (including sand and gravel) and other non-ore minerals up to 30 years, for underground waters and natural non-combustible gases up to 25 years. A license for the study of the subsoil is issued for up to 5 years. Keep in mind that extracting inert material from a riverbed is prohibited in some zones, for example in the coastal protection strip of the sea.

After obtaining the license

With a license, you may use the subsoil only for the established purpose and within the territory defined by the license. You must observe safety rules and protect the environment. The conditions of the license are monitored by the Environmental Supervision Department. If you do not begin using the subsoil within the deadlines set by the license, the right may be revoked.

Conclusion

A license is mandatory for the lawful extraction of minerals. Self-willed use ends without compensation for the expenses incurred and entails liability. The process begins with an application and ends with the issuance of the license. Before the auction is announced it must not exceed 4 months, and you will receive the license on the 10th working day after payment of the final amount. The process can be sped up, but this will entail additional cost. Prepare the application in advance and attach the full documents, because you will have only 5 working days to correct a defect.