When Losing a Tender Feels Like Injustice
A company spent months preparing for a state tender and met every requirement, but another company won, and under circumstances that cast doubt on the integrity of the procedure. Many people, in such a case, think the dispute is already over. In reality, the law offers the aggrieved bidder a specific mechanism, but on one condition: the deadline is strictly limited, and it is often the missed deadline, not the merits of the complaint, that decides the fate of the case.
This article examines who can file a complaint, where it can be filed, what deadlines apply, and what a successful complaint achieves.
The Council or the Court
The law offers the bidder two options. The first is the Dispute Resolution Council operating at the State Procurement Agency - an independent body appointed by the Prime Minister for a term of 5 years, with 5 members. The second option is applying directly to the court.
Applying to the Council is faster and cheaper, the process takes place entirely electronically, in a special module of the system. However, the Council's decision is not final: either party can challenge it in court. The right to appeal does not apply equally to everyone. A complaint may be filed by:
- a person wishing to participate in the procurement, or a bidder, if the claim concerns the tender or competition announcement or documentation;
- only a bidder, if they believe that the rules for their selection and evaluation were violated after the submission of proposals began;
- a person registered in the system with "supplier" status, in cases of simplified procurement where the value of the procurement exceeds the thresholds established by the EU directives applicable in the field of public procurement, and the complaint concerns a decision related to the conclusion of the contract.
In addition, the law directly excludes the appeal of certain decisions, for example, if the matter concerns the appropriateness of the choice of procurement method, or a decision made to lawfully suspend the procedure.
The Deadline - the Decisive Factor
This is where the most common mistake lies. Missing the deadline automatically means the complaint is inadmissible, regardless of how well-founded the claim may be on the merits.
The tender or competition documentation can only be appealed before the submission of proposals begins. A decision related to the selection, evaluation, or disqualification of bidders can be appealed within 10 days of the decision being uploaded to the system or the action being carried out, but always only before the contract is concluded.
In practice, this means that after the contract is signed, the possibility of applying to the Council is already lost. The only exception is a decision related to the conclusion of a simplified procurement contract carried out due to urgent necessity.
The Fee Is Increasing
Filing a complaint is not free, the fee is 2% of the estimated value of the procurement. Under the rule in effect until now, this amount ranged from 100 to 500 GEL and was paid by bank card as soon as the complaint was filed; if the complaint was upheld, it was refunded. However, under the legislative amendment of June 23, 2026, which took effect on September 1, 2026, these thresholds increased substantially: the fee is now a minimum of 500 GEL and a maximum of 1000 GEL. Anyone planning to prepare a complaint now needs to take this change into account.
What Happens After the Complaint Is Filed
The Council decides on the admissibility of the complaint within 2 working days. If the complaint was filed by an unauthorized person, in violation of the deadline, or on another legal ground, the Council declares it inadmissible. If the complaint contains only a formal defect, the complainant is given 1 working day to correct it, otherwise the complaint is automatically considered inadmissible.
As soon as the complaint is declared admissible, the procurement procedure is automatically suspended, the procuring organization is obliged not to make any decision until the case is finally resolved. The Council then hears the complainant, the respondent, and, if necessary, interested parties and experts, and makes a final decision within 10 working days; if the case requires additional examination, this period may be extended by another 10 days.
If the complaint is upheld, the Council can require the procuring organization to repeat the procedure in accordance with the law, to revise or annul the decision, and, in the case of a serious violation, to also raise the question of the responsible person's liability before the competent authorities.
Conclusion
The appeal mechanism genuinely works, but it depends almost entirely on deadlines. The 10-day period, which mostly runs before the contract is concluded, practically leaves no time for later reflection. A company that believes its rights were violated in a tender needs a quick and precise legal assessment so that the complaint is formulated on time and without defects, the Council declares it admissible, and examines the case on the merits.