A hydropower plant (HPP) project cannot exist without water, and in Georgia water is the property of the state. Therefore, before starting construction of an HPP, an investor must determine on what legal basis river water may be used. In practice, this right is often called a water use license, although the law refers to it as a special water use permit. The 2023 law “On Water Resources Management” reorganized the entire sector. Below we discuss what takes effect and when, how the right to use water is obtained, and what an HPP project must take into account.
What Took Effect and When
The new law repealed the 1997 law “On Water”. This happened on September 1, 2026, and from the same day the main part of the law also applies, including the water resources management system and the rules on state ownership of water. The permitting regime itself, that is, the rules on issuing permits, their term of validity and refusal, will take effect on September 1, 2027. Municipalities will issue permits for water resources of local significance from January 1, 2030.
Acts issued under the old law remain in force until they are repealed or until new acts are issued under the new law, provided they do not contradict the new law. The government must approve the detailed rules and conditions for issuing permits by September 1, 2027.
This means that we are now in a transitional period: the old law has already been repealed, while the new permitting regime will take effect one year later. Therefore, for a project planned today, the specific practice must be clarified with the Ministry of Environmental Protection and Agriculture (hereinafter the Ministry).
Water Is State Property
Water resources are state property. Land ownership does not give the owner the right to use a river or groundwater passing through the land. An exception is common water use, that is, non-commercial, personal use where no structure or device that significantly affects the condition of the water body is used. No permit is required in this case.
When a Special Water Use Permit Is Required
Special water use means using water by means of a structure or device that significantly affects the condition of the water body. The law names as a significant effect, for example, the abstraction of more than 15 cubic meters of water per day from a surface water body. An HPP generally falls within this regime, since it uses a large volume of water; in addition, the law separately sets the permit term for HPP water use.
The law recognizes three types of permit: a water abstraction permit, a water discharge permit, and a combined permit covering both.
HPP and the Environmental Decision
Whether an environmental impact assessment (EIA) applies to an HPP project is determined by the Environmental Assessment Code and depends on the characteristics of the project.
Under the water law, if an activity is subject to an EIA, the person obtains the right to use water on the basis of an environmental decision, without a separate permit. In this case, the term and conditions of water use are determined by the water law and the decision itself. An environmental decision is issued for an indefinite term; however, if the activity does not begin within 7 years, the National Environmental Agency declares it invalid.
From September 1, 2027, the date the permitting regime takes effect, the Environmental Assessment Code will also change. If an activity involves special use of surface water, the application for an environmental decision must be accompanied by the documentation required by the water law. During the transitional period, the practice must be clarified with the Ministry.
A separate permit is still required in the following cases: when the water use term set by the decision expires and when the conditions of water abstraction or discharge change after the decision is issued, but this does not entail a change in operating conditions. If the change also alters the operating conditions, it must go through the procedure established by the Environmental Assessment Code, and the documentation required for the permit is submitted within that same procedure.
Under a transitional provision, a person who already holds an environmental decision before the new permitting regime takes effect continues water use under the conditions of that decision. If the conditions change, however, the rules described above apply.
Permit Term
A permit on a surface water body is generally issued for a term of up to 5 years. The exceptions are irrigation systems, where the term is up to 25 years, drinking water supply, where it is up to 30 years, and a hydropower or thermal power plant, where the term is up to 49 years. In the case of an HPP, the term is determined according to the term provided for in the agreement concluded with the state.
In addition, in the event of a significant natural change in water quantity due to climate change, the issuing authority may review the issued permit and amend it.
How a Permit Is Issued
The permit is issued by the Ministry within 45 calendar days. To obtain a water abstraction permit, the application must be accompanied, in addition to the general permitting documents, by a brief technical description of the activity, water use parameters, a schematic plan of the water use system, if one exists, a location plan with the coordinates of the abstraction points, and a hydrological and qualitative description of the water body.
When making its decision, the Ministry takes into account the river basin management plan and the river’s environmental flow, that is, the water that must remain in the river to sustain the ecosystem. In addition, drinking and household needs have priority. If a municipality plans to supply the population with water from the same water body, this circumstance is taken into account when the decision is made. In the border zone and border strip, a permit is issued in agreement with the relevant body of the Ministry of Internal Affairs.
The law also directly lists the grounds for refusal: violation of the requirements of the Law on Licenses and Permits or other legal acts, inaccuracy of the submitted information, the absence of wastewater treatment equipment in the case of discharge, and a conflict between issuing the permit and the legislation. A refusal may be appealed to a higher administrative body or to a court.
What to Pay Particular Attention to in the Case of an HPP
The law prohibits taking water from a river and constructing and operating a hydrotechnical facility without taking the river’s environmental flow into account. This provision will take effect on September 1, 2027. From the same day, permits on surface water bodies will be issued in accordance with the environmental flow assessment methodology approved by the minister.
Filling a reservoir is prohibited until the measures provided for preparing its basin have been implemented. This prohibition has been in effect since September 1, 2026. From September 1, 2027, a natural resources use fee must be paid for taking water from a surface water body through special water use. This also applies to persons who hold an environmental decision.
Control and Liability
Control over water use, including compliance with permit conditions and the suppression of unlawful water use, is carried out by the Environmental Supervision Department of the Ministry. Liability for violating the law is determined by the legislation in force. This liability does not release the offender from the obligation to compensate for damage caused to the environment.
Conclusion
The right to use water for an HPP project is obtained in two ways. Under the general rule, water is state property and its special use requires a permit issued by the Ministry. If the project is subject to an EIA, the right is obtained through an environmental decision, while a separate permit may become necessary after the term set by the decision expires or the water use conditions change. The permit term for an HPP is up to 49 years and depends on the term of the agreement concluded with the state. Since the permitting regime will take effect on September 1, 2027, the legal structure of the project must be clarified in advance with the Ministry during the transitional period.